Appendix E.

HONGKONG, 27th July, 1889.

Appendix E.

STATEMENT shewing approximate cost of repairing Damages caused by the Rain-storm of 29th and 30th of May, within the City of Victoria.

Hon. SURVEYOR GENERAL,

I forward herewith revised estimate for "Repair of Storm damages." The present state of the work of repairs is as given below.

Cemetery. The nullah has been cleared, the dry rubble retaining walls have been re-built wher they were washed away and raised near the lower boundary so as to retain the heap of sand that was partly washed down and partly taken out of the nullah, the mound itself has been formed and i being covered with earth."

The upper bridge has been restored.

The brick boundary wall has been re-built.

The arch of the bridge which carries the road between the Cemetery and race course is being repaired and will be completed in about 10 days.

Race Course. The debris which has been taken out of the nullah and placed on the paddock will at once be levelled and formed as arranged with the Clerk of the Course.

The repairs of Bowrington bridges are in hand and will not be finished for two months, probably, as the foundations have to be put in as the tide allows.

Levelling Debris on Race Course,

Bridge at Bowrington, re-building Walls adjacent,

Slip at Bowringtou,

Sundry small jobs,

Queen's Road near Naval Yard,

Repair Upper part Albany Nullah,- Albany Nullah,.

Repairs Parapet Bridge,

Albany Nullab, work done by Military,

fee House Lane, clearing,

Zetland Street, clearing Street,

Do. do., renewing Road,

Clearing Pedder's Street and Wyndham Street,

All slips and debris have been removed in the Eastern district and drains cleared the roads in Clearing Glenealy Ravine above the top of Wyndham Street up to the open Hill,... this part are in fairly good order the necessary repairs are being carried out.

Albany Nullah-The temporary bamboo bridge on the Queen's Road has been removed and the water is running again under the stone arch. The clearing of the debris is going on quickly and expect to have the uullab clear in about 3 weeks.

The repairs to the parapet of the bridge have not yet been put in hand.

Names of Place damaged.

*

Cemetery,

547

Re-building Rubble Walls,

170

Forming Mound and re-making Paths,

150

Re-building Walls of Upper Bridge and re-fixing Bridge,

155

Re-building portion of Lower Bridge,

60

Re-building Boundary Wall,

153

230

1,465

1,300

526

Naval Hospital,..

398

Nullah Lane, Wauchai Road, including Branch Nullab, Ship Street,

592

340

100

1,956

480

3,000

1,460

100

7,040

384

430

300

364

2,256

1,205

Covering in Drain from the sea to the bottom of Wyndham Street and making good

Paving, &c.,

482

Repairing Sewer in Wyndham Street to the bottom of Glenealy,

1,010

Repairing Sewer in Glenealy including taking up and re-setting Steps,... Making open Nullah above the Caine Road,

2,360

5,000

Re-building all retaining Walls, Glenealy,..

2,200

Making good Paths, filling in large Holes, &c....

2,500

18,107

35

37

200

90

290

90

50

160

100

180

228

172

Queen's Road West,

91

160

Re-building Drain,

162

160

Drain on Road below Nullah Side,

Re-building granite culvert High Street, Nullah Side,.

980

100

Western Nullah,

11

Shektougtsui Nuliah,

Repairing Drain and Road, Western Nullah,.

414

26

Repairs Upper Richmond Road,

190

and

Lower Richmond Road, clearing,

45

276

Robinson Road,..

68

54

Staunton Street,

27

16

36

10

25

178

135

86

4,884

2,000

Glenealy, Wyndham Street and Pedder's Street.--The repairs in Pedder's Street are very nearly finished the remainder of the paving stones of the footpath will be relaid in a few days, and this will complete every thing.

The two holes in the drain opposite the Club in Wyndham Street will be finished and the road made good certainly in a week.

It will be necessary to open another place in the drain near the German Club to repair the invert but this will not be open more than a week.

The repairs of the drain above this point as far us and including the hole in the Caine Road are in hand and should be finished nearly in two months.

The bank which carries the path which has been carried away just below the Caine Road is being renewed and should be completed in about six weeks.

A contract is being made for the repairs of the nullah above Caine Road.

The large open nullah above where the ventilator stands has been repaired where necessary is in good order.

The repairs of the roads in the Central part of the town are being carried on.

Western District. To the west the only piece of building that remains to be done is the re-build ing of the drain under High Street. A contract has been made for this and the work will be carried out at once. All debris has been removed and inlets to drains and drains have been cleared in the Western district the roads in this district being steep have suffered a great deal. The repairs are in hand.

H. CHAMPERNOWNE,

Hollywood Road,

Elgin Street, Shelley Street, Seymour Rond,

Castle Road,

Peel Street and Queen's Road, Hospital Road,

Bonham Road, Pokfulam Road,

West end of Third Street,

Centre Street,

Praya West, clearing,

Chinese Hospital, clearing and examining,

Nullah Side,

Renewing Road,

Caine Road,

Lyndhurst Terrace,

Clearing Inlet of Culvert near Western Street on Bonham Road, Clearing Inlet Sand Street Sewer,

Smithfield Street, Sand Street Sewer,

Do.

Davis Street, Sand Street Sewer,

Do.

Filling in and repairing Smithfield Street, &c., Skle Channel, Clearing Landslip, Mount Davis Road,

Minor Repairs to Roads,

Total,...

37,136

Lient-Colonel, R.E.

H. CHAMPERNOWNE, Lieut.-Colonel, R.E.